Solving grid congestion: 7 options for your business

November 04, 2026

On the waiting list for a bigger grid connection? Seven options for a business facing grid congestion, and a worked example: a 40 kW expansion that goes over the limit in only 1.1% of the year.

In short

A business that cannot get a bigger grid connection because of grid congestion has seven options: shifting consumption, absorbing peaks with a battery, using its own generation smarter, congestion management, an alternative transport right, sharing capacity or a connection, and waiting. Which one fits depends on when, and for how long, the connection is full. Quarter-hour data shows you that.

What grid congestion is

Congestion is another word for a traffic jam. With grid congestion the cables are too busy at certain moments: no more power can flow through part of the grid than already does. It can happen in two directions: on import, when too much power is demanded at once in an area, and on feed-in, when too much is fed back at once.

A business in such an area that applies for more transport capacity ends up on a waiting list. On 30 June 2026 the Dutch regional grid operators had 15,498 requests for more import capacity on their lists, nearly 10,000 MW together, and 8,558 for feed-in. According to the grid operators, the wait can run to several years1. Whether your area is full is shown on the capacity map of Netbeheer Nederland (in Dutch), the association of Dutch grid operators.

The grid is being expanded, but in many regions the number of applications grows faster. That is not the fault of the business that wants to grow, nor of the grid operator. The grid was built for a time when businesses burned gas, filled up with diesel and hardly fed anything back.

What the waiting list means for your business

A large connection has a contracted transport capacity: the most you may take from or feed into the grid in any quarter hour. On the waiting list that maximum stays where it is, and that has consequences.

  • Expanding or electrifying has to fit within the current capacity. The new hall, the charge points or the heat pump add to what is already there.
  • An overrun gives you no rights. Liander, one of the Dutch grid operators, treats an overrun as a request to raise the transport capacity. Outside congested areas that usually happens automatically, in a congested area it does not2.
  • A generous contract is not a safe buffer. In congested areas the grid operator may limit transport capacity that has not been shown to be needed, after consulting the business3.

So a business that waits for capacity cannot grow for now. The question is what does fit within the current connection, and for that you need to know how full it really is.

A connection is rarely full all year

Take the wholesaler from how many EV chargers fit on my grid connection: an office and a warehouse on one connection with 160 kW of contracted transport capacity. The highest quarter hour of 2025 is 132 kW. The business is fictional; its profile was built for that article, quarter hour by quarter hour, over all of 2025.

The business builds a second warehouse hall. Lighting, ventilation and doors need 25 kW together on working days from 6:00 to 16:00. Four electric forklifts charge during the same shift at 15 kW on average, 150 kWh per working day. Together that is 40 kW extra, and the highest quarter hour becomes 172 kW: 12 kW above the transport capacity. More capacity is not available, because the area is full.

Yet consumption only goes above 160 kW in 379 of the year's 35,040 quarter hours, 1.1% of the time. All of them fall on working days between 8:45 and 15:15, and three in four in December, January and February, when the building's existing heat pump works hardest.

Three in four of the quarter hours above the limit fall in winter

Quarter hours above 160 kW per month, with the new hall and the forklifts charging during the shift

Quarter hours above 160 kW per month, with the new hall and the forklifts charging during the shift
January136 quarter hours
February55 quarter hours
March13 quarter hours
April10 quarter hours
May3 quarter hours
June13 quarter hours
July33 quarter hours
August7 quarter hours
September2 quarter hours
October0 quarter hours
November11 quarter hours
December96 quarter hours
379 quarter hours in all, of which 287 in December, January and February. Not one in October. Source: the constructed profile of the example business over 2025, calculated with the Wattix engine.

The longest unbroken stretch above the limit is on Friday 10 January, from 9:30 to 14:30. Over those five hours, 25 kWh sits above 160 kW in all, and 11 kW in that day's highest quarter hour.

Five hours above the limit on 10 January, with a peak of 171 kW

Consumption per quarter hour on 10 January between 6:00 and 20:00. From 6:00 it rises, from 9:30 to 14:30 it is above the transport capacity of 160 kW, with a peak of 171 kW at 11:00. After 16:00 it drops quickly, to about 50 kW in the evening.

Friday 10 January 2025, with the hall and the forklifts charging during the shift. Source: the constructed profile of the example business, calculated with the Wattix engine.

Measured at the peak, the expansion does not fit. Measured per quarter hour, it already fits for 98.9% of the year. Which of the seven options works depends on those 379 quarter hours: when they fall, how long they last and how many kWh sit above the limit.

Kremer
“Our clients want to grow. Extra warehouses, machines, production lines. But they can't get additional capacity from the grid operator. Wattix helps us show what's still possible within their existing connection.”
Jesse Moms, Kremer Installatietechniek

Seven options for grid congestion

1. Shift consumption

Not all consumption has to happen at the time it happens now. Machines can run in another shift, vehicles can charge later and cooling can be done in advance. For consumption that can wait, shifting is the cheapest option, because nothing needs to be added.

In the example the forklifts no longer charge during the shift but from 16:00 to 2:00, with the same 150 kWh. The highest quarter hour of the year then becomes 157 kW, and not one quarter hour goes above 160 kW.

With the forklifts after 16:00, 10 January stays under the limit

Consumption per quarter hour on 10 January between 6:00 and 20:00, with the forklifts charging after 16:00. It rises to 156 kW around 11:00 and stays under the transport capacity of 160 kW all day. After 16:00 it drops more slowly than without shifting, because the forklifts are charging.

The same day, with the forklifts charging from 16:00 to 2:00. Consumption reaches 156 kW that day. Source: the constructed profile of the example business, calculated with the Wattix engine.

The margin is small: less than 3 kW in the busiest quarter hour of 2025, a year without a cold spell. A colder winter can still push a few quarter hours over the limit. How to plan charging within the limit when more vehicles are involved is covered in smart charging in Wattix.

2. Absorb peaks with a battery

A battery charges when there is headroom under the transport capacity and discharges as soon as consumption goes above it. Its size follows from the quarter hours above the limit: the power from the highest overrun, the storage capacity from the most kWh that build up above the limit before it can recharge.

For the example without shifting, the Wattix engine arrives at a battery of 12.2 kW and 33.3 kWh, with 85% efficiency and a minimum charge of 10%. That storage capacity does not follow from 10 January but from Wednesday 26 February, the day of the highest quarter hour: between 9:00 and 13:15 consumption goes nearly 28 kWh above 160 kW in all, with hardly any room to recharge in between. With the battery, the business does not draw more than 160 kW from the grid in a single quarter hour of 2025. How to work out such a size yourself, and why rules of thumb make it too small, is covered in sizing a battery for a business.

A battery that only absorbs peaks stands idle most of the year. In this calculation, with a fixed power price, it delivers 265 kWh a year.

3. Use your own generation smarter

With congestion on feed-in, this is the main option. A business that is not allowed to feed back solar power can use more of it itself, cap what it feeds back, or switch off when feeding back costs money. How that works out on a large connection is covered in negative power prices and solar panels.

With congestion on import, your own generation only helps if it is there at the moment of the peak. In the example, three in four of the quarter hours above the limit fall in the winter months, when solar panels generate least.

4. Congestion management

With a capacity steering contract (capaciteitssturingscontract) you agree with the grid operator that it may have you lower or raise your consumption at busy moments, in return for a fee. The steering can be on request, or always within fixed time windows such as the daily peak hours. On 30 June 2026 there were 375 of these contracts for import, 270 of them on request. Grid operators also approach businesses on the waiting list with flexible offers, such as a contract like this or an alternative transport right, and can grant part of the requests that way after all1.

A contract like this needs consumption that you can really adjust, on request or in the agreed windows, without work coming to a halt. In the example that is the forklifts: their charging can wait a few hours, the lights in the hall cannot.

5. An alternative transport right

With an alternative transport right you do not always have the full transport capacity, and you pay a lower grid tariff4. There are three forms1:

  • Time-block transport right: transport within agreed time blocks outside the peak moments, for example to charge a fleet at night. The regional grid operators offer this.
  • Time-duration transport right: transport in at least 85% of the hours. For the rest, the grid operator announces a day ahead whether there is capacity, and how much. Only TenneT, the national grid operator, offers this, on the high-voltage grid.
  • Fully variable transport right, also called non-firm: transport in a congested area at moments when there is room. The grid operator announces a day ahead at the latest when, and how much. At most grid operators this can only be used to a limited extent so far.

Whether an alternative transport right is available differs per area. And it has to match the profile. In the example the extra capacity is needed precisely on working days during the day. A time block in the off-peak hours does not help the hall, but it does help consumption that can already move to the evening or the night. How to check a profile against a time block is explained at compare energy contracts.

6. Share capacity or a connection

With a group transport agreement (groepstransportovereenkomst), several large consumers sign one transport agreement together, while each business keeps its own connection. The ACM, the Dutch regulator, set the rules in December 20255. With cable pooling, up to four nearby installations for generation, storage or consumption share one connection of at least 100 kVA6.

Sharing works when the businesses or installations peak at different moments. A warehouse that peaks during the day fits better next to a cold store that runs at night than next to a second warehouse.

7. Apply and wait

Waiting is an option too, and it does not rule out the others. When capacity becomes available, the grid operator allocates it according to the social prioritization framework: first parties that reduce congestion, then hospitals, housing and schools, among others1. Businesses without social priority wait longest.

Liander releases capacity in a large part of Gelderland and the Flevopolder from 1 January 2027, and reviews it every six months. For businesses that stay on the waiting list, Liander itself points to flexible energy use and better use of the existing connection7. Those are the options above.

Which option fits

OptionFits if you haveIn the worked example
1. ShiftingConsumption that can waitForklifts after 16:00: peak 157 kW
2. BatteryRoom to recharge in between12.2 kW and 33.3 kWh
3. Own generationGeneration during the peakHelps little: peaks in winter
4. Steering contractConsumption that can drop for a whileThe forklifts' charging
5. Transport rightConsumption outside the peak hoursNot for the hall
6. SharingNeighbors who peak at other momentsNot calculated
7. WaitingSocial priorityNo priority, so at the back of the queue

The answer can also be a combination: first shift what can be shifted, then absorb the rest with a smaller battery or a different contract. To choose, you need four things from a year of the connection's quarter-hour data, with the expansion added:

  1. In how many quarter hours consumption goes above the transport capacity.
  2. When: at which hours, on which days and in which months.
  3. How long the longest stretch above it lasts, and how many kWh sit above it.
  4. Which part of the consumption can wait or drop for a while.

A year is needed because the tightest days often fall in winter. From the highest peak alone you cannot see the first three.

What Wattix does here

In Wattix you set the quarter-hour data of a connection against its contracted transport capacity, add the expansion and see, quarter hour by quarter hour, where consumption goes above it. Then you calculate the options as scenarios side by side: a different consumption profile, smart charging within the limit, a battery, solar panels, or a contract with a different limit per hour and per weekday, such as a time-block transport right. The worked example was calculated with the same engine. How this works for a business facing grid congestion is covered in grid congestion.

Frequently asked questions about grid congestion

What is grid congestion?

Grid congestion means that part of the electricity grid is full: at certain moments no more power can flow through it than already does. That can apply to taking power from the grid, to feeding it in, or to both. A business in such an area that applies for a bigger connection or more transport capacity ends up on a waiting list.

How long does it take to get a bigger grid connection?

In a congested area it can take several years, according to the Dutch grid operators. On 30 June 2026 the regional grid operators had 15,498 requests for more import capacity on their waiting lists. When capacity becomes available, it goes first to parties that reduce congestion and to social functions such as hospitals, schools and housing.

Can I go over my transport capacity while I am on the waiting list?

Not in the expectation that it gets you the capacity. Liander treats an overrun as a request to raise the transport capacity, and an overrun without permission gives you no rights. Outside congested areas Liander then usually raises the contract automatically, but not in a congested area, where the waiting list applies. The rules differ per grid operator.

Can the grid operator take back unused transport capacity?

In congested areas it can, since a code decision by the Dutch regulator ACM in April 2024. It applies to connections on the medium, high and extra-high voltage grid, and there to large amounts of transport capacity that have not been shown to be needed. The grid operator must consult the business first. A generous contract is therefore not a safe buffer there.

What is the difference between a capacity steering contract and an alternative transport right?

With a capacity steering contract you agree that the grid operator may have you lower or raise your consumption at busy moments, in return for a fee. With an alternative transport right you do not always have the full transport capacity, only within agreed time blocks or for part of the hours, and you pay a lower grid tariff. The first needs consumption that can be adjusted for a while, the second consumption that already fits outside the peak hours.

What is a group transport agreement?

A group transport agreement is one transport agreement for several large consumers together, while each business keeps its own connection. The ACM set the rules in December 2025. It helps when the businesses peak at different moments, so that together they need less capacity than each would on its own.

Do I need a battery against grid congestion?

Not always. A battery only absorbs the kWh that go above the transport capacity, and then has to be able to recharge. In the worked example 12.2 kW and 33.3 kWh is enough, but moving the forklifts' charging solves the same problem without a battery.

The grid is full.
Show what still fits.

In a demo you see how to get from metering data to a recommendation you can back up. Bring your own data and we look at your case right away.

Sources

  1. Landelijk Actieprogramma Netcongestie, the Dutch national grid congestion action program, Actualisatie van de voortgang, najaar 2026 (in Dutch), its progress update of October 2026, with figures from Netbeheer Nederland's Stand van de Uitvoering: the waiting lists on 30 June 2026, "De wachttijd kan oplopen tot meerdere jaren", the wait can run to several years, the 375 capacity steering contracts for import, 270 of them on request, the three forms of alternative transport rights and the social prioritization framework. ↩ ↩2 ↩3 ↩4

  2. Liander, Tarieven voor aansluiting en transport elektriciteit 2026 (in Dutch): "Dan beschouwen wij deze overschrijding als aanvraag tot verhoging van uw gecontracteerde transportvermogen. Aan een overschrijding zonder voorafgaande instemming van Liander kunt u geen rechten ontlenen", Liander then treats the overrun as a request to raise the contracted transport capacity, and an overrun without its prior consent gives no rights. The automatic increase applies "behalve in congestiegebieden voor dezelfde energierichting", except in areas congested in the same direction. ↩

  3. ACM, Codebesluit niet-gebruikte transportrechten (GOTORK) (in Dutch), the code decision on unused transport rights, 16 April 2024: for connections on the medium, high and extra-high voltage grid in congested areas, for substantial amounts of transport capacity that have not been shown to be needed. ↩

  4. ACM, Codebesluit alternatieve transportrechten (in Dutch), the code decision on alternative transport rights, 16 July 2024: "Aangeslotenen die gebruik maken van een alternatief transportrecht betalen een lager nettarief", connected parties that use an alternative transport right pay a lower grid tariff. ↩

  5. ACM, Codebesluit groepstransportovereenkomst (in Dutch), the code decision on the group transport agreement, 11 December 2025. ↩

  6. RVO, the Netherlands Enterprise Agency, Netaansluiting delen (in Dutch), checked by RVO on 3 July 2026: "U mag één aansluiting delen met maximaal 4 installaties (WOZ-objecten)", you may share one connection with at most 4 installations, on a connection of at least 100 kVA. ↩

  7. Liander, Gelderland en Flevopolder ruimte voor nieuwe aansluitingen, rondom Doetinchem onvoldoende ruimte (in Dutch), 2 November 2026: "Flexibel energiegebruik en efficiënter gebruik van een bestaande aansluiting kan mogelijkheden bieden", flexible energy use and more efficient use of an existing connection can offer possibilities. ↩